Project Cost: $3,495,162.77
Completion: December 2016
Contract Method: Firm Fixed
The project at NAS Whiting Field was a design/build underground medium voltage distribution project that included new manholes, duct banks, switchgear, sectionalizing cabinets, 15kv cables, terminations and extensive coordination with the owner for scheduling outages. The distribution voltage at Whiting Field is 5KV however, all new switchgear, cable, substation, and components were rated 15KV, anticipating a future system upgrade to that voltage. Whiting Field is one of the busiest airfields in the United States with continual pilot training activities. The project involved a complete replacement of the incoming electrical service from the utility including: