Project Cost: $1,674,563.00
Completion: June 2011
Contract Method: Firm Fixed Price
This project involved replacing the existing overhead electrical distribution system with a new 15kV underground system. A new 15kV manhole and duct bank system with high-voltage switches, sectionalizing cabinets, and transformers was provided. New decorative street lights and controllers were provided along with landscaping around the new pad-mounted equipment.