Contract Number P0014558. Project No. 1718-011
The nature of the firm’s responsibility on the project: Prime Contractor
Project was completed January 2021
Size of project: $1,062,934.00
Cost of project (construction cost): $850,051.00
This project consisted of removing a 40-year-old 12 Bay line up of existing 15kV primary switchgear located inside of the Main powerhouse at UWF and replacing with a New 50 Ton outdoor Stainless Steel 15kV primary PCR – (Power Control Room) Manufactured by Powell Manufacturing Houston, Texas
This project included the following:
New Underground Vault and Service Pad to support the New 15kV PCR
Concrete Vault & Pad dimensions 50’L x 18’W x 8’
20,000’ 15kV 500 MCM EPR 133% Primary cable MV 105
< 80 > 600A 15kV t-bodies
< 27 > 15kV 500 MCM Cold shrink terminations
< 2 > 600A Cooper VFI Switches 5 ways
< 1 > 45’ Concrete Pole & Riser for Main Feed from Utility Company